APRIL NEWSLETTER

Some further, good progress made on site during April.

 

The higher temperatures and less rain had meant that the site dried out making life much easier.

 

As the four terraced houses are now fully waterproofed, our carpenter has completed the stud wall partitions having

boarded the floors, and the staircases have been fitted to all floors.

 

All windows and doors are also installed subject to a small snagging list which the fitters are to resolve.

 

The electrical and plumbing first fixes are also close to completion.

 

Our Senior Building Inspector has revisited prior to pre-plaster stage as agreed and he is happy with progress.

 

He has also inspected the groundworks undertaken in respect of services and has similarly given his approval.

 

So far, progress is being made with gas, electricity, water, BT cabling and drainage and we hope to have this all in place

during May.

 

Please enjoy the images below and we look forward to updating you again in a month’s time.

 

Kind regards

 

Kevin and the team